This project proposes to replace the existing SR 25/Main Street Bridge over Pipemakers Canal in Garden City, Georgia.  The project involves the extension, widening and reconstruction of the SR 25 Bridge over Pipemakers Canal.  The new bridge will be raised in order to span Pipemakers Canal as well as a critical transportation corridor required by the Georgia Ports Authority's Port of Savannah International Multi-Modal Connector.  This corridor will include six arrival, departure and runaround tracks, the relocated Foundation lead, a two-way driveway, and two two-way, on-terminal service roads.  In order to construct the new bridge, SR 25 will be closed at Pipemakers Canal and detoured for up to 12 months. 

A Public Information Open House for the project was held February 28, 2017.  See attached flyer for additional information.