Current Construction Projects  

 

Pipemakers Canal, Phase 2, Section 2
10/01/2012 - 08/30/2014

Storm drainage improvements to the Pipemakers Canal from west of Dean Forest Road to east of I-95. Project consists of channel deepening and widening, upgrade of tributary culverts and construction of maintenance roadways along both sides. Project will increase conveyance capacity and reduce upstream water surface elevations. Project is expected to be completed by August, 2014.

Walthour Road / Betz Creek Bridge Replacement
04/07/2014 - 11/30/2014

It is on Walthour Road at Betz Creek on Wilmington Island. The project includes removal and replacement of the existing bridge and related roadway improvements. The work is underway now and should be complete by November of 2014. The contract was awarded to TIC.

Hunt and Faye Drive Bridge Replacements
05/01/2013 - 01/01/2015

The Hunt Drive Bridge Replacement Project is proposed to remove and replace the existing deteriorated bridge on Hunt Drive. The construction contract was awarded to Rogers Bridge Company on February 22, 2013. Notice to proceed with construction was issued to the contractor on May 1, 2013. The new bridge is expected to be completed in June 2014. Once the Hunt Drive bridge replacement is complete, the contractor will mobilize to replace the existing, deteriorated bridge on Faye Drive. One-way traffic across the bridges will be maintained at all times using temporary traffic signals during construction. -------- UPDATE: The contractor is mobilzed on Faye and upon its completion, both bridges will recieve a final paving to complete the entire project.

LaRoche Avenue Culvert Replacement
01/27/2014 - 10/30/2014

Replacement of failing brick arch culvert conveying storm drainage beneath LaRoche Avenue between Neva Avenue and Lansing Avenue. Project consists of culvert replacement and localized roadway improvements and requires closure of LaRoche Avenue. Project will remove concerns of in-service failure while improving stormwater conveyance capacity. Project expected to be completed by October, 2014.

Turner Creek Boat Ramp Improvements
06/10/2014 - 08/31/2015

The Turner Creek Boat Ramp Improvements project consists of the construction of a new concrete boat ramp, floating dock, concrete block building featuring separate men’s and women’s restroom facilities, picnic pavilion, parking improvements and an additional access drive from the east bound lane of Johnny Mercer Boulevard. The construction contract was awarded to The Industrial Company (TIC) on March 28, 2014. The project is expected to be completed by August 2015. Construction shall be staged so as to have a minimum of one boat ramp open for ingress/egress at all times.

Dean Forest Road Widening, Phase 2
07/16/2014 - 05/31/2015

The project includes widening from two lanes to four lanes with a center median on Dean Forest Road from U.S. 17/ Ogechee Road to 0.5 miles north. Reeves Construction Doing Business As (DBA) R.B. Baker Construction was awarded the project on May 9, 2014. Construction should be complete by May of 2015.

Jennifer Ross Soccer Drop-Off and Parking Project
07/11/2014 - 11/30/2014

The Jennifer Ross Soccer Complex Drop-Off Loop and Parking Project will provide additional parking and an access road from Eisenhower Drive. The project consists of paving, grading, drainage improvements and landscaping. The construction contract was awarded to Pioneer Construction, Inc. on July 11, 2014. The project is expected to be completed by November 2014.

Development

Applications

Flood Zones

Flood Zones

SPLOST Projects