Current Construction Projects  

 

Pipemakers Canal 24" Pipe Replacement
11/01/2014 - 03/01/2015

Chatham County wull replace undersized pipes with larger culverts.

Hampton Place Drainage Improvements
09/22/2014 - 03/01/2015

Chatham County plans to install storm inlets near the entrance of Hampton Place. The County will also replace a portion of the asphalt roadway on Vineyard Haven Drive from Quacco Road to West Tisbury Lane. There will be traffic detours during the construction of the project.

Montgomery Cross Rd @ Sallie Mood Intersection
07/11/2014 - 01/12/2015

Removal and replacement/upgrade of the existing traffic signal at Montgomery Cross Road and Sallie Mood Drive, as well as installation of pedestrian and pavement improvements.

Hunt and Faye Drive Bridge Replacements
05/01/2013 - 01/01/2015

The Hunt Drive Bridge Replacement Project is proposed to remove and replace the existing deteriorated bridge on Hunt Drive. The construction contract was awarded to Rogers Bridge Company on February 22, 2013. Notice to proceed with construction was issued to the contractor on May 1, 2013. The new bridge is expected to be completed in June 2014. Once the Hunt Drive bridge replacement is complete, the contractor will mobilize to replace the existing, deteriorated bridge on Faye Drive. One-way traffic across the bridges will be maintained at all times using temporary traffic signals during construction. -------- UPDATE: The contractor is mobilzed on Faye and upon its completion, both bridges will recieve a final paving to complete the entire project.

Shipyard Road Channel Improvements
09/02/2014 - 01/10/2015

Chatham County will replace culverts and widen the drainage ditch from Shipyard Road near Railroad Avenue to Montgomery Baptist Church.

Turner Creek Boat Ramp Improvements
06/10/2014 - 08/31/2015

The Turner Creek Boat Ramp Improvements project consists of the construction of a new concrete boat ramp, floating dock, concrete block building featuring separate men’s and women’s restroom facilities, picnic pavilion, parking improvements and an additional access drive from the east bound lane of Johnny Mercer Boulevard. The construction contract was awarded to The Industrial Company (TIC) on March 28, 2014. The project is expected to be completed by August 2015. Construction shall be staged so as to have a minimum of one boat ramp open for ingress/egress at all times.

Bamboo Farm Entrance Improvements
09/18/2014 - 01/16/2015

Entrance and Parking Improvements to the existing entrance into the Coastal Georgia Bamboo Farm on Canebrake Road.

Dean Forest Road Widening, Phase 2
07/16/2014 - 05/31/2015

The project includes widening from two lanes to four lanes with a center median on Dean Forest Road from U.S. 17/ Ogechee Road to 0.5 miles north. Reeves Construction Doing Business As (DBA) R.B. Baker Construction was awarded the project on May 9, 2014. Construction should be complete by May of 2015.

LaRoche Avenue Culvert Replacement
01/27/2014 - 11/30/2014

Replacement of failing brick arch culvert conveying storm drainage beneath LaRoche Avenue between Neva Avenue and Lansing Avenue. Project consists of culvert replacement and localized roadway improvements and requires closure of LaRoche Avenue. Project will remove concerns of in-service failure while improving stormwater conveyance capacity. Project expected to be completed by October, 2014.

Pipemakers Canal Tide Gate Replacement
11/01/2014 - 05/01/2015

Replacement of existing sluice gate system with flap gates over the outfall box structure.

Jennifer Ross Soccer Drop-Off and Parking Project
07/11/2014 - 11/30/2014

The Jennifer Ross Soccer Complex Drop-Off Loop and Parking Project will provide additional parking and an access road from Eisenhower Drive. The project consists of paving, grading, drainage improvements and landscaping. The construction contract was awarded to Pioneer Construction, Inc. on July 11, 2014. The project is expected to be completed by November 2014.

Development

Applications

Flood Zones

Flood Zones

SPLOST Projects